Bathroom Renovation Timeline Greenwich (2027): Day by Day

By Cormac Hegarty, Director & Founder - Buildaway

Cormac Hegarty is the Founder of Buildaway and a residential construction specialist with a deep portfolio of projects across London.

Updated • 9 min read
White marble-effect shower room with a navy vanity, a Buildaway project shown in our Bathroom Renovation Timeline Greenwich guide

A bathroom refit is one of the shortest projects we run in Greenwich, but it is also one of the most disruptive, because most households have only one bathroom. Knowing what happens on each day lets you plan showers, school runs and work around the fitters.

Our Greenwich page does not publish a day count, so this guide uses the London-wide figures from our bathroom guide and walks through a standard family refit one day at a time, from strip-out to the final clean.

Key Takeaways
  • A standard family bathroom renovation typically takes 9-14 days on site (London-wide figure from Buildaway's bathroom guide (checked November 2026)).
  • A like-for-like suite swap is shorter, at 5-9 days on the same London-wide basis.
  • Bathroom prices in Greenwich start from around £4,000 (Buildaway's typical project range, checked November 2026); larger projects quoted per project.
  • Flats on Greenwich Peninsula usually need the landlord's licence for alterations before work starts.
  • Bathrooms rarely need planning permission, but electrics, ventilation, hot water and drainage must meet building regulations.
How long does a bathroom renovation take in Greenwich?

A standard family bathroom renovation usually takes 9-14 days on site, and a like-for-like suite swap 5-9 days, using the London-wide figures from our bathroom guide. Greenwich prices start from around £4,000, with larger projects quoted per project. Leasehold flats may need landlord consent before the first day.

What must be ready before day one?

Before the fitters arrive, the design should be signed off and the key items should be on site or confirmed for delivery. That means the bath or shower tray, toilet, basin, vanity, taps, tiles and adhesive. Starting without them is the most common reason a short refit stretches into extra days.

In a Greenwich Peninsula flat there is one more task: getting the landlord's licence for alterations. Most leases require written consent for work that touches plumbing, waterproofing or the floor, and managing agents can take a while to reply.

In the period terraces of West Greenwich, check whether the house is listed. Listed building consent is needed for alterations that affect the character of a listed building, including some internal work, and the Royal Greenwich planning service can confirm the position.

What happens on days 1 and 2?

Days one and two are strip-out and inspection. The old suite, tiles and flooring come out, waste is removed, and the walls and floor are checked for damp, rot or loose plaster. In older Greenwich terraces this is when hidden problems, such as a rotten joist under the bath, usually appear.

We protect floors, stairs and the hallway before anything is carried out. In a terraced house the bathroom is often at the back of the first floor, so the route through the house needs covering for the whole job.

Any repair found here is agreed with you before the team moves on. Because the room is now empty, it is also the best moment to confirm where the new fittings will sit and to mark out pipe and cable runs on the walls.

What gets done on days 3 and 4?

Days three and four are first fix. The plumber moves or extends supply and waste pipes to suit the new layout, and the electrician runs cables for lighting, an extractor fan and any heated towel rail or shaver socket. All of this has to be done before walls are boarded or tiled.

Electrical work in a bathroom is notifiable under Part P of the building regulations, so it must be done by a registered electrician or signed off by building control. The extractor fan also matters, because Part F sets minimum extract rates for bathrooms.

Waste pipe falls are checked at this stage, because Part H covers drainage and a poor fall causes slow-draining showers later. Hot water safety, including the temperature at the bath, falls under Part G.

When are the walls boarded and waterproofed?

Boarding and waterproofing usually fill days five to seven. Walls around the shower or bath are lined with tile backer boards, the floor is levelled or boarded, and a tanking membrane is applied to wet areas. The membrane needs time to cure before tiling, so this stage cannot be rushed.

Any boxing for pipes or a concealed cistern is built now as well, using moisture-resistant board, so the tiler has a solid surface to work on.

Waterproofing is especially important in Greenwich flats, where a leak can damage the flat below. A well-tanked shower area protects you, your neighbours and your relationship with the managing agent.

If underfloor heating is part of the design, the mat or pipework is laid on the prepared floor at this stage and tested before tiles go down. Testing now avoids lifting a finished floor later.

How long does tiling take in a Greenwich bathroom?

Tiling in a standard bathroom usually takes several days, and our bathroom guide notes that a tiler typically needs 3-4 days for full-height tiling. Large-format or patterned tiles take longer, because cutting and setting out need more care. Grouting and sealing follow once the adhesive has set.

Period bathrooms in West Greenwich often have walls that are not quite straight. Our tilers check the walls before setting out, so the grout lines look even even where the old plaster is uneven.

Silicone sealing around the bath, tray and basin is the last part of tiling. It needs a day to cure before the shower is used, which is why the bathroom usually stays out of action until handover.

What happens on the final days?

Second fix and handover take the last days of a standard refit. The toilet, basin, vanity, taps and shower are connected, the electrician fits the lights and fan, and the room is sealed, cleaned and tested. We then walk through everything with you and show you how each fitting works.

A typical standard refit lands within 9-14 days, the London-wide range from our guide. Simpler like-for-like jobs often finish within 5-9 days, while wet rooms run longer because of the extra waterproofing.

At handover you receive the electrical certificate and any product guarantees. Keep them with your house paperwork, because a buyer's conveyancer or your managing agent may ask to see them later.

Which Greenwich bathrooms take longer than average?

Three kinds of Greenwich bathroom tend to run beyond a standard refit. Wet rooms need extra floor waterproofing and take 12-18 days on the London-wide basis. Layout changes add plumbing work, and period houses with uneven walls or old floor joists need repairs before any new finishes go on.

Moving a toilet is the biggest single change, because the soil pipe has to reach the main stack with a proper fall. In a West Greenwich terrace that often means lifting floorboards in the room below or boxing the pipe in, both of which add time.

Peninsula flats bring different constraints. Many have concrete floors with limited depth for waste pipes, so a walk-in shower may need a raised tray or a pumped waste. Working hours are also usually set by the building's management, which can mean shorter days.

Premium fit-outs with bespoke joinery or underfloor heating sit at the top of the scale, and our guide gives 14-22 days for that level. We confirm which category your bathroom falls into during the survey.

Greenwich bathroom refit day plan at a glance

The table shows how the stages fit together on a standard refit, so you can plan around the days the bathroom is completely out of use.

Day-by-day plan for a standard bathroom refit in Greenwich
DaysWorkBathroom usable?
1-2Strip-out and inspectionNo
3-4First fix plumbing and electricsNo
5-7Boarding, levelling, tankingNo
8-11Tiling, grouting, sealingNo
12-14Second fix, testing, handoverFrom handover
Source: Buildaway refit pattern within the 9-14 day London-wide figure from Buildaway's bathroom guide (checked November 2026).

Day ranges overlap slightly in practice, because plaster and adhesive drying times decide when the next trade can start. We confirm the exact sequence for your room after the survey.

How long will it take if you start in 2027?

A 2027 refit follows the same sequence and the same London-wide ranges, because the work involved does not change with the year. The start date depends mainly on when your design is signed off and when sanitaryware and tiles can be delivered.

We do not rely on any forecast for 2027 timings or prices. Lock in a fixed quote and book early, and confirm product lead times before the start date is set.

How to prepare your Greenwich home for a refit

A little preparation makes the days easier for everyone in the house, especially in a one-bathroom home or a Peninsula flat.

  1. Confirm landlord or listed building consent if your home needs it.
  2. Order sanitaryware and tiles early so they are on site before day one.
  3. Arrange alternative washing facilities for the days the bathroom is out of use.
  4. Clear the room and the route to it, including the hall and stairs.
  5. Agree parking or a loading spot for deliveries and waste removal.

With those steps done, the team can start on time and keep the programme moving from strip-out to handover, without pauses while decisions or deliveries catch up.

Greenwich bathroom timeline FAQs

Answers to the timing questions Greenwich homeowners and Peninsula leaseholders most often ask us in the weeks before they book a refit.

Do Greenwich Peninsula flats need consent for a new bathroom?

Usually yes. Most leases need a licence for alterations from the landlord before work that touches plumbing, waterproofing or floors. Ask your managing agent early, because a late reply can delay the start date.

How many days will we be without a bathroom in Greenwich?

For a standard refit, expect the room to be out of use for most of the 9-14 days in our London-wide guide. A like-for-like swap is shorter, at 5-9 days, so plan alternative washing facilities for that period.

Does a listed house in Greenwich need consent for a bathroom refit?

It can. Listed building consent is needed for work that affects a listed building's character, which may include some internal alterations. Check with the Royal Borough of Greenwich before you finalise the design.

Should we book a Greenwich bathroom refit now for 2027?

If you want a particular start date, yes. We have no forecast for 2027 prices or timings, so we advise you to lock in a fixed quote and book early, with products ordered ahead of time.

What does a Greenwich bathroom renovation cost?

Bathroom projects in Greenwich start from around £4,000 (Buildaway's typical project range, checked November 2026). Larger projects quoted per project, after a free survey of the room and its plumbing.

Book your Greenwich bathroom refit

Buildaway is an FMB member, gives fixed written quotes and backs every bathroom with an 18-month workmanship warranty. Call 0208 108 0388 or email info@buildaway.co.uk, see our Greenwich bathroom fitters page and our bathroom renovation service.

Read our London bathroom renovation guide, the Greenwich bathroom fitter checklist and the building regulations approved documents before your survey.

About the author
By Cormac Hegarty, Director & Founder - Buildaway. Cormac Hegarty is the Founder of Buildaway and a residential construction specialist with a deep portfolio of projects across London.

Where is Buildaway based?

Buildaway is based in Chislehurst, a short drive from Greenwich, Blackheath and Charlton.

Nearby Areas We Serve

Nearby areas where Buildaway designs and fits bathrooms.

Get a fixed quote for your Greenwich bathroom

Tell us about your bathroom and we will arrange a free survey.

Planning a bathroom in Greenwich? Get a fixed quote and a free survey.

Call 0208 108 0388 Get a Free Quote