A Beckenham kitchen has two timelines. The first runs before anyone arrives: design, ordering and, in many Victorian and Edwardian houses, structural design for a knock-through. The second is the time on site, which our Beckenham page puts at 2 to 4 weeks once work starts.
This guide covers both. It starts with the lead times you need to plan for, then walks through the site work week by week for a typical renovation, including the extra steps when a wall comes down and a steel beam goes in.
- Most Beckenham kitchen renovations take 2 to 4 weeks once work starts, according to our Beckenham page.
- Full kitchen renovations typically cost £8,000-£18,000, and installation labour alone £2,000-£5,000 (Buildaway's typical project range (checked November 2026)).
- Lead times for units, worktops and appliances vary by supplier, so confirm them in writing before setting a start date.
- Removing a load-bearing wall needs a structural engineer, building control approval and, for a party wall, a Party Wall notice.
- Gas work must be done by a Gas Safe registered engineer, and kitchen electrics must comply with Part P.
Our Beckenham page says most kitchen renovations take 2 to 4 weeks once work starts. Before that, allow for design and for unit, worktop and appliance lead times, which vary by supplier. Full renovations typically cost £8,000-£18,000, with installation labour alone at £2,000-£5,000, according to Buildaway's typical project range.
What has to happen before work starts?
Before work starts, the design must be signed off, every item ordered and any structural work approved. That means the layout, units, worktop material, appliances, sink and taps are all chosen. In a Beckenham knock-through, the structural engineer's calculations and building control approval must also be in place.
| Item | Lead time | Why it matters |
|---|---|---|
| Kitchen units | Varies by supplier | Needed on day one of fitting |
| Stone or quartz worktops | Varies by supplier; made after templating | Sets the end date |
| Appliances | Varies by supplier | Needed for second fix |
| Steel beam | Made after calculations are approved | Needed in week one |
| Source: Buildaway practice; we confirm each lead time with the supplier in writing. | ||
Lead times vary by supplier and by product, so we confirm each one in writing before fixing your start date. Starting with anything missing is the most common reason a kitchen overruns.
Bespoke units and stone worktops usually take longer than standard ranges, and worktops cannot be made until the base units are fitted and templated. That sequence is built into the site plan below.
What extra planning does a Beckenham knock-through need?
A knock-through between the kitchen and dining room is common in Beckenham's Victorian and Edwardian houses. If the wall is load-bearing, a structural engineer designs the beam and supports, and building control approves the calculations. If the wall is shared with a neighbour, a Party Wall notice is needed as well.
The Party Wall etc. Act 1996 requires notice before work that affects a party wall, and the government Party Wall guidance explains the notice periods. Serving notices early keeps them from delaying the start date.
Steel beams are made to order once the calculations are approved. Ordering promptly means the beam is ready for week one, when the wall comes out.
Victorian houses often have chimney breasts beside the old kitchen wall. If a breast is removed on the ground floor, the masonry above must be supported, which the engineer designs at the same time as the beam.
What happens in week 1?
Week one is strip-out and structure. The old kitchen is removed, services are isolated, and if there is a knock-through, temporary supports go in and the wall is removed and replaced with a steel beam. Building control usually inspects the beam before it is covered, and first fix plumbing and electrics begin.
In older Beckenham houses, strip-out often uncovers uneven floors, old wiring or tired plaster. Dealing with them now is quicker than discovering them after the units are in.
Dust control matters most this week. We seal doorways with temporary screens and protect floors through the house, because Victorian and Edwardian homes in Beckenham often have original floorboards or tiled hallways worth keeping intact.
First fix means running new pipes and cables to where the sink, appliances, lights and sockets will go. Kitchen electrics must meet Part P, and any gas pipework must be handled by a Gas Safe registered engineer.
What happens in week 2?
Week two prepares the room for the new kitchen. Walls are plastered or made good, the floor is levelled and, if it is going in before the units, laid. Once plaster is dry, base and wall units are fitted, and the worktops are templated so they can be cut to exact sizes.
On a straightforward renovation with laminate or wood worktops, fitting may finish this week. Stone and quartz worktops take longer, because they are cut after templating, which is why many kitchens run into week three or four.
Underfloor heating and new flooring are best laid before the units in a knock-through, so the floor runs continuously from the kitchen into the dining area. Screeds need drying time, which we plan into this week.
What happens in week 3?
Week three is usually worktops and second fix. Worktops are fitted, the sink and hob are installed, and appliances are connected. The electrician fits sockets, switches and lighting, and the Gas Safe engineer connects and tests any gas hob. Splashbacks and tiling follow once the worktops are in place.
If the worktops are laminate or timber, this week often finishes the job. If they are stone or quartz, fitting depends on when the fabricator delivers after templating, and that timing varies by supplier.
Tiled splashbacks need a day for adhesive and grout to set before the hob area is used. Glass or stone upstands are measured with the worktops and fitted when they arrive.
What happens in week 4?
Week four, where it is needed, covers the finishing work: decorating, final adjustments to doors and drawers, sealing, and a full clean. Knock-through projects and kitchens with stone worktops are the ones most likely to need this week. The job ends with a walk-through and the certificates.
The certificates include the electrical installation certificate under Part P, the Gas Safe certificate for any gas work and, for a knock-through, the building control completion certificate. Keep them with your house documents.
We also hand over the appliance manuals and warranties, and show you how to adjust hinges and drawer runners. Small tweaks in the first few weeks are normal as the units settle into place.
Beckenham kitchen site plan at a glance
The table pulls the four weeks together. A simple renovation may finish in two, while a knock-through with stone worktops usually takes the full four on our Beckenham page.
| Week | Main work | Applies to |
|---|---|---|
| 1 | Strip-out, wall removal and beam, first fix | All; beam for knock-throughs |
| 2 | Plaster, floor, units fitted, worktops templated | All kitchens |
| 3 | Worktops, sink, hob, appliances, second fix | All; stone may extend |
| 4 | Decorating, adjustments, clean, certificates | Knock-throughs and stone |
| Source: Buildaway project pattern within the 2 to 4 weeks on the Beckenham kitchen fitters page (checked November 2026). | ||
What does a Beckenham kitchen cost?
Full kitchen renovations in Beckenham often fall between £8,000 and £18,000, depending on design and materials, and installation labour typically ranges from £2,000 to £5,000, according to Buildaway's typical project range. Knock-through work involving a steel beam adds structural costs, which are quoted per project after the engineer's design.
The difference between the labour figure and the full renovation figure is mostly units, worktops and appliances. Owners who buy their own kitchen and ask us only to install it pay the labour figure plus any extra work found on site.
Extras that commonly appear in Beckenham period houses include rewiring an old circuit, levelling a sloping floor and moving a radiator to free wall space for units.
How long will it take if you start in 2027?
A 2027 kitchen follows the same 2 to 4 week site plan, because the work involved does not change. What varies is how long the run-up takes, which depends on your design decisions, supplier lead times and, for a knock-through, the engineer and building control.
We do not use a forecast for 2027 timings or prices. Lock in a fixed quote and book early, and order units and appliances well ahead of the start date.
How to plan a Beckenham kitchen timeline
Follow these steps to keep the run-up short and the site work within the page range, whatever size of kitchen you are planning.
- Finalise the layout, units, worktop material and appliances.
- For a knock-through, appoint a structural engineer and apply to building control.
- Serve Party Wall notices if the wall is shared with a neighbour.
- Order units, worktops, appliances and the steel beam, and confirm lead times in writing.
- Set up a temporary kitchen in another room.
- Agree a fixed written quote and a start date once everything is confirmed.
Getting these steps done before the start is what allows a Beckenham kitchen to be finished within 2 to 4 weeks on site.
Beckenham kitchen timeline FAQs
Answers to the timing questions Beckenham homeowners ask us most often when they are planning a new kitchen and a temporary one.
Does a steel beam add much time to a Beckenham kitchen?
On site it mainly affects week one, when the wall is removed and the beam installed. The bigger effect is beforehand, because the engineer's design, building control approval and beam manufacture must all be done before the start.
Why do stone worktops take longer to fit?
Stone and quartz worktops are cut to exact measurements taken after the base units are fitted. The fabricator then makes them, and that lead time varies by supplier, which is why stone kitchens often run into week three or four.
Do I need planning permission for a Beckenham kitchen?
Usually not, because a kitchen renovation is internal work. Building regulations still apply to structural changes and electrics, and a listed building may need consent. Check with Bromley Council if you are unsure.
When should I order units for a 2027 Beckenham kitchen?
As soon as the design is fixed, because lead times vary by supplier. We have no forecast for 2027, so lock in a fixed quote and book early once every item is confirmed.
Can we still cook during a Beckenham kitchen renovation?
Not in the kitchen itself. Most families set up a temporary kitchen in another room with a microwave, kettle and fridge for the 2 to 4 weeks on site.
Plan your Beckenham kitchen
Buildaway is an FMB member, gives fixed written quotes and backs every kitchen with an 18-month workmanship warranty. Call 0208 108 0388 or email info@buildaway.co.uk, see our Beckenham kitchen fitters page and our kitchen renovation service.
Read the London kitchen cost guide, our Beckenham kitchen pitfalls article and check engineers on the Gas Safe Register.
By Cormac Hegarty, Director & Founder - Buildaway. Cormac Hegarty is the Founder of Buildaway and a residential construction specialist with a deep portfolio of projects across London.